Technical Group - Problem Status Report
RCC MEETING on Mar 15, 2006
|
Started |
Priority |
Responsible |
Problem |
Action |
Status |
|
1/06, 2/06, 3/06 |
1 |
Ryan |
All channels off air during
recabling |
|
Channels 50 and 51 have
returned to the air |
|
1/06 |
2 |
Ryan/ Richard |
New room layout |
Need logic diagram of
interconnections |
Mostly done. |
|
1/06 |
3 |
|
Channel 51 – dead signal
during updates |
Will be able to use XSN
function |
Will be fixed when
Enterprise level of XSN is installed. |
|
10/05 |
4 |
Richard |
Equipment approved for 2006
purchase |
Apple G5 System (2) XSN Systems for Channels 50 & 52 Switcher and Keyer Surge Protectors (High Quality) |
Here: Apple G5, Tripod, (2) XSN Systems Researching switcher and
keyer Surge protector order
awaiting room layouts |
|
2/06 |
5 |
|
Audio quality |
Shooting and playback |
|
|
2/06 |
6 |
Ryan |
Create methodology for new
systems |
|
|
|
2/06 |
7 |
|
Define new procedures and
train volunteers |
Assign when methodology is
created |
|
|
11/05 |
8 |
All |
HDTV |
Broadcast analog TV
terminates in 2009 – need to discuss what actions we need / want to take |
Broadcast Committee has
meeting scheduled for March 20. Briefing
paper is being written. |